If the specimen height H is 24mm and height of solids Hs is 13.45mm, then find the voids ratio.

(a) 0.786

(b) 0.432

(c) 2

(d) 34

This question was addressed to me during an interview.

My question comes from Consolidation Problems topic in section One Dimensional Consolidation of Geotechnical Engineering I

1 Answer

+1 vote
by (727k points)
selected by
 
Best answer
Correct choice is (a) 0.786

The best I can explain: Given,

H=24mm

Hs  =13.45mm

\(e=\frac{H-H_s}{H_s}\)

\(e=\frac{24-13.45}{13.45}\)

e=0.786.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...