The foundations of bridges on erodible beds are taken down below the HFL by an amount equal to _____________

(a) 4/3 times the maximum scour depth

(b) 2/3 times the maximum scour depth

(c) 1.5 times the maximum scour depth

(d) 2 times the maximum scour depth

This question was addressed to me in homework.

The above asked question is from Small Road Bridges Construction topic in section Culverts and Small Road Bridges Construction of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct option is (a) 4/3 times the maximum scour depth

Explanation: The value is taken down below HFL by 4/3 times the maximum scour depth or Max scour depth + 2 (for arched bridges) and Max scour depth + 1.2 for other bridges (whichever is more). The formula is applicable where there is no bed floor is provided under the structure.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...