A siphon aqueduct is constructed at a canal crossing site where drainage HFL was 212.2 m by allowing an afflux of 0.4 m at high flood discharge. At this site, the water level downstream of the crossing at the same high flood will be _________

(a) 212.2 m

(b) 212.6 m

(c) 211.8 m

(d) It cannot be predicted

I got this question in exam.

The origin of the question is Cross Drainage Work Design topic in division Cross Drainage Work of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct choice is (a) 212.2 m

Explanation: The D/s HFL of the drain remains the same by the construction of works and the U/s HFL can be obtained by adding afflux to the D/s HFL.

The D/s water level = 212.2 m

The U/s water level = 212.2 + 0.4 = 212.6 m.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...