What is Lacey’s equation for fixing the approximate value of the required waterway for the drain?

(a) P = 4.75 Q

(b) P = 4.57 Q

(c) P = 4.75 Q^1/2

(d) P = 4.57 Q^1/2

I have been asked this question at a job interview.

My question is taken from Cross Drainage Work Design in division Cross Drainage Work of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct answer is (c) P = 4.75 Q^1/2

For explanation: The correct equation for fixing the waterway requirement for Aqueduct and Syphon-Aqueducts is given by P = 4.75 Q^1/2 where P is the wetted perimeter in meters and Q is the total discharge in cumecs. The wetted perimeter may be taken equal to the width of the drain and equal to the waterway required in case of wide drains.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...