Which CD work is generally adopted when the drainage discharge is small and the drain crosses the canal with its bed level equal to or slightly higher than the canal FSL?

(a) Syphon Aqueduct

(b) Level crossing

(c) Inlets and outlets

(d) Aqueduct

This question was posed to me in quiz.

This interesting question is from Types of Cross Drainage Work in portion Cross Drainage Work of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct option is (c) Inlets and outlets

The best I can explain: Level crossing is generally adopted when the canal and the drainage are practically at the same level and for high flood drainage discharge but short-lived. Aqueduct or super passage is adopted when high flood drainage discharge is large.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...