The crossing arrangement preferably made at the junction of a huge canal and a river stream carrying a short-lived high flood discharge at almost equal bed levels is a __________

(a) super passage

(b) aqueduct

(c) level crossing

(d) canal syphon

This question was posed to me by my college professor while I was bunking the class.

I'd like to ask this question from Types of Cross Drainage Work topic in division Cross Drainage Work of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct answer is (c) level crossing

For explanation: This is a type of cross-drainage works in which the canal water and the drain get intermixed. The arrangement is generally adopted when a huge canal crosses a large torrent carrying a high short-lived flood.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...