+1 vote
in Irrigation Engineering by (75.2k points)
In order to keep the saturation line in a canal embankment well within the toe, it is necessary to provide _____________________

(a) spoil bank

(b) counter berm

(c) freeboard

(d) berm

I had been asked this question during an online interview.

My enquiry is from Failure of Earthen Dams topic in chapter Earthen and Rock Fill Dams of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right option is (b) counter berm

To explain: The saturation gradient line may cut the downstream end of the bank even after providing sufficient section for bank embankment. By the provision of counter-berms, the saturation line can be kept covered at least by 0.5 m.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...