If the peak load for a power plant equals the plant capacity then the ratio of the capacity factor to load factor will be _________________

(a) 1

(b) 0

(c) < 1

(d) > 1

The question was posed to me during an interview.

Origin of the question is Hydropower in division Hydro Electric Power of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct option is (a) 1

For explanation I would say: Load factor = Average load over a certain period / Peak load during that period

Capacity factor = Average load over a given time period / Plant capacity

Since, Plant capacity = Peak load

Ratio of CF / LF = 1.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...