+1 vote
in Irrigation Engineering by (75.2k points)
As per estimate made by the Central Electricity Authority, the potential of the country is accessed at 84 GW at load factor value of _________________

(a) 40%

(b) 60%

(c) 80%

(d) 20%

I had been asked this question in my homework.

The doubt is from Hydro Electric topic in section Hydro Electric Power of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right answer is (b) 60%

To elaborate: This equivalent to about 440 billion units + KWh of annual energy generation at a power factor of 0.6. 60% load factor means that the installed machines are run on an average to give output capacity equal to 60% of the station capacity. Machines will not always work at the installed capacity but on an average of 60% of this capacity.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...