If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___________________
(a) 35%
(b) 50%
(c) 70%
(d) 65%
The question was posed to me at a job interview.
The above asked question is from Hydropower in division Hydro Electric Power of Irrigation Engineering