If the peak load on a power plant having a capacity of 100 MW is 70 MW during a given week and the energy produced is 58, 80,000 kWh, the capacity factor for the plant for the week will be ___________________

(a) 35%

(b) 50%

(c) 70%

(d) 65%

The question was posed to me at a job interview.

The above asked question is from Hydropower in division Hydro Electric Power of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right answer is (a) 35%

Explanation: Capacity factor = Average load/ Plant capacity

Average load = Energy produced / Time (in hours) = 58,80,000 / 7 x 24 = 35000 kW

C.F = 35 MW / 100 MW = 0.35 (or 35%).

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...