The correct sequence in the direction of the flow of water for installations in a hydropower plant is _______________________

(a) Reservoir, Surge tank, Turbine, Penstock

(b) Reservoir, Penstock, Surge tank, Turbine

(c) Reservoir, Penstock, Turbine, Surge tank

(d) Reservoir, Surge tank, Penstock, Turbine

I have been asked this question in an online interview.

My question comes from Principal Components of a Hydro Electric Scheme in division Hydro Electric Power of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct choice is (b) Reservoir, Penstock, Surge tank, Turbine

For explanation: The main components of a hydropower plant is Forebay, intake arrangement, Penstock, Surge tank, turbines and generators, powerhouse and tailrace. The water is taken from a reservoir or forebay and is taken down to the powerhouse by penstock. A surge tank is fitted at some opening made on a penstock to receive the rejected flow when the pipe is suddenly closed.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...