The type of canal alignment which involves maximum CD works is a ______________

(a) ridge canal

(b) contour canal

(c) side slope canal

(d) both ridge and contour canal

The question was asked during an online exam.

My question is taken from Cross Drainage topic in chapter Cross Drainage Work of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right option is (b) contour canal

The best I can explain: A watershed line or ridgeline crosses the minimum number of drains and contour canal crosses the maximum number of drains. When a canal is aligned as contour canal it requires more CD works. It is a costly construction and should be avoided as far as possible.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...