If the spillway is constructed in continuation to the dam at one end, it may be called as ________

(a) saddle weir

(b) flank weir

(c) waste weir

(d) temporary weir

I got this question at a job interview.

This is a very interesting question from Chute Spillway topic in section Spillways, Energy Dissipators and Spillway Gates of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right option is (b) flank weir

For explanation I would say: Saddle weir is the one when the spillway is constructed in a natural saddle in a bank of the river separated from the main dam by a high ridge. Flank weir is the one when the spillway is constructed in continuation to the dam at one end.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...