Correct option is (b) (s2 – s1) d1
Best explanation: Berm is the horizontal distance between the toe of the bank and top edge of the cutting. If s2 : 1 is the slope in filling and s1 : 1 is the slope in cutting, and the initial depth of the berm from the bed of the canal is d1 then width of the berm is (s2 – s1) d1. As d1 varies, the width of the berm also varies. As siltation occurs the formula is (s2:1/2) y (y=over all new depth of the berm).