Which type of structure does the diagram represent?

(a) Borrow Pit

(b) Freeboard

(c) Spoil Banks

(d) Berm

I have been asked this question during an online interview.

Question is from Cross-Section of an Irrigation Canal in portion Sediment Transport and Irrigation Channels Design of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct answer is (a) Borrow Pit

For explanation: Clearly the diagram represents the excavation of pit of width less than half the width of the canal and the depth of the pit is less than 1 m. So, therefore according to this information we can say that the diagram represents a borrow pit. And more information we can obtain from the diagram is that the borrow pit is an internal borrow pit.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...