The actual capacity of silt laiden water channel is worked out with 1/2 : 1 side slopes.

(a) True

(b) False

I have been asked this question in unit test.

Enquiry is from Cross-Section of an Irrigation Canal in portion Sediment Transport and Irrigation Channels Design of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right choice is (a) True

Easy explanation: Flatter slopes such as 1 : 1 and 1.5 : 1 are also constructed at the time of execution, but actual capacity of channel is worked out in 1/2 : 1 slope because even if we provide 1 : 1 or 1.5 : 1 slope the silt gets deposited on this slope and gives a new side slope 1/2 : 1. Therefore the actual capacity is calculated using 1/2 :  1 slope.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...