By providing a natural drop in one drop _______________________

(a) the quantity of unbalanced earthwork decreases

(b) the quantity of unbalanced earthwork increases

(c) the quantity of balanced earthwork increases

(d) number of fall increases

The question was posed to me in exam.

The question is from Canal Falls in division Canal Falls of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct answer is (b) the quantity of unbalanced earthwork increases

For explanation: The number of fall decreases and the quantity of unbalanced earthwork increases by providing a larger drop in one step. All these factors have to be worked out before deciding the locations and extent of falls.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...