________ is the time required by flood discharge to reach the maximum limit.

(a) Storm frequency

(b) Run-off time

(c) Detention period

(d) Time of concentration

This question was addressed to me by my school principal while I was bunking the class.

I'm obligated to ask this question of Rational Method in section Water Supply for Building, Collection and Conveyance of Sewage, Waste Water Flow Rate of Environmental Engineering

1 Answer

+2 votes
by (693k points)
selected by
 
Best answer
The correct option is (d) Time of concentration

For explanation I would say: The time of concentration is defined as the longest time required for a drop of water to flow from the farthest point of drainage area to the point of concentration.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...