Depending on how many considerations the capacity of under sluices is fixed?

(a) 5

(b) 4

(c) 2

(d) 3

I have been asked this question in a job interview.

My doubt is from Diversion Head Works and its Components in division Diversion Head Works, Hydraulic Jump Usefulness in Irrigation Structure of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right option is (d) 3

Explanation: The discharging capacity of an under sluice is fixed by the considerations like to ensure proper scouring and its capacity should be double the canal discharge, sluices should of sufficient capacity to discharge winter freshlet, and during floods 10 to 15 percent of maximum flood discharge should be done.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...