The number of hectares irrigable per cumec of the canal capacity at its head is known as ____________

(a) nominal duty

(b) duty on capacity

(c) design full supply discharge

(d) capacity factor

This question was posed to me by my college professor while I was bunking the class.

I need to ask this question from Canal Irrigation System in portion Canal Irrigation System of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct option is (b) duty on capacity

To explain: Full supply coefficient is also called duty on capacity. It is the design duty at the head of the canal. It is obtained by dividing the area estimated to be irrigated during the base period with the design full supply discharge at the head of the canal.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...