+1 vote
in Irrigation Engineering by (75.2k points)
A canal which when fully developed yields enough revenue to cover up its running cost is known as _____________

(a) protective canal

(b) productive canal

(c) permanent canal

(d) inundation canal

I have been asked this question in exam.

This key question is from Canal Irrigation System in portion Canal Irrigation System of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right answer is (b) productive canal

For explanation: After the development of the canal system the revenue obtained from the cultivators is such that it is more than the maintenance expenditure. This exceeding amount of revenue is so adjusted that it is about 2% of the cost of the canal system. With this rate, the total cost of the project will be recovered in about 50 years.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...