In bored pile, concreting is done by using ___________

(a) Auger

(b) Casing tube

(c) Under-reamer

(d) Concrete plug

The question was asked in an international level competition.

The above asked question is from Bored Piles topic in division Pile Foundations of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
The correct choice is (b) Casing tube

The explanation is: Bored piles are done by forming a bore hole in the ground and then concreting it, either with the help of a casing tube.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...