A major difference between the procedure of construction in bored piles and cast-in-situ driving piles is ___________

(a) Driving equipment

(b) Method of driving

(c) Concrete filling

(d) None of the mentioned

I had been asked this question in a national level competition.

The doubt is from Bored Piles topic in portion Pile Foundations of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
Correct choice is (a) Driving equipment

Explanation: The procedure of construction in bored piles is different than the cast-in-situ driven pile where heavy pile driving equipment is required.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...