A major difference between the procedure of construction in bored piles and cast-in-situ driving piles is ___________
(a) Driving equipment
(b) Method of driving
(c) Concrete filling
(d) None of the mentioned
I had been asked this question in a national level competition.
The doubt is from Bored Piles topic in portion Pile Foundations of Geotechnical Engineering II