Which of the following has minimum detention period?

(a) Grit chamber

(b) Sedimentation tank

(c) Oxidation ditch

(d) Oxidation pond

I have been asked this question in a national level competition.

My doubt is from Grit Chambers, Tanks and Vacuum Floatation in portion Unit Operations for Wastewater Treatment, Preliminary Treatment of Environmental Engineering

1 Answer

+2 votes
by (693k points)
selected by
 
Best answer
The correct choice is (a) Grit chamber

The best I can explain: Grit chamber has a minimum detention period with a value of 40-60 seconds.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...