For dewatering more than 6m below the water table, which of the following method is used?

(a) Well point system

(b) Multi stage well point system

(c) Vacuum method

(d) Deep well system

The question was posed to me during an interview.

My question comes from Well Point System topic in chapter Drainage and Dewatering of Geotechnical Engineering I

1 Answer

+1 vote
by (727k points)
selected by
 
Best answer
The correct option is (b) Multi stage well point system

For explanation I would say: Multi stage well point system at precise distances is used for dewatering more than 6m below the natural water table.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...