For dewatering more than 6m below the water table, which of the following method is used?
(a) Well point system
(b) Multi stage well point system
(c) Vacuum method
(d) Deep well system
The question was posed to me during an interview.
My question comes from Well Point System topic in chapter Drainage and Dewatering of Geotechnical Engineering I