In vacuum method, the top of bore hole is sealed by __________

(a) soil cement

(b) bentonite

(c) clay

(d) soil cement, bentonite and clay

The question was posed to me during an online exam.

I want to ask this question from Drainage and Dewatering in chapter Drainage and Dewatering of Geotechnical Engineering I

1 Answer

+1 vote
by (727k points)
selected by
 
Best answer
Right answer is (d) soil cement, bentonite and clay

For explanation: The coarse sand is shovelled into the hole to fill upto about 0.75m to 1m from the top.  The top portion of the bore hole is sealed up by tamping soil cement, bentonite or clay.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...