+1 vote
in Irrigation Engineering by (75.2k points)
The process of laying and compacting earth in layers by power rollers under OMC for construction of earthen dams is known as ______________________

(a) Rolled fill method

(b) Hydraulic fill method

(c) OMC method

(d) Compaction

I have been asked this question in examination.

The query is from Types of Earthen Dams in section Earthen and Rock Fill Dams of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Correct option is (a) Rolled fill method

For explanation I would say: In the rolled-fill method, the embankment is constructed by placing suitable soil materials in thin layers and compacting the layers with rollers. Power-operated rollers are used for dams and ordinary road rollers can be used for low embankments. The best compaction can be obtained at the optimum moisture content (OMC).

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...