Correct answer is (a) 5 m
Explanation: Bligh has given an empirical formula for finding out the thickness of the dam at top.
A = 0.522 H^1/2 = 0.522 x 84^1/2 = 5.05 m.
As per Creager, the economical top width has been found to be equal to 14% of the dam height without considering earthquake forces.