The maximum aeration period for a conventional activated sludge system is ___________

(a) 2 hours

(b) 3 hours

(c) 4 hours

(d) 6 hours

I have been asked this question by my college director while I was bunking the class.

This key question is from Design of Activated Sludge Plant in portion Sewage Filtration and Activated Sludge Process of Environmental Engineering

1 Answer

+2 votes
by (693k points)
selected by
 
Best answer
The correct option is (d) 6 hours

Easiest explanation: The detention period for a conventional activated sludge system is between 4 to 6 hours.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...