+2 votes
in Environmental Engineering by (81.4k points)
Which of the following has minimum hydraulic retention time?

(a) Conventional process

(b) Extended process

(c) Modified aeration process

(d) Complete mix process

I had been asked this question in examination.

The doubt is from Design of Activated Sludge Plant topic in portion Sewage Filtration and Activated Sludge Process of Environmental Engineering

1 Answer

+2 votes
by (693k points)
selected by
 
Best answer
Correct choice is (c) Modified aeration process

Best explanation: Modified aeration process has a minimum hydraulic retention time with an aeration period of 1.5 hours.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...