After landfill unit receives last shipment of hazardous waste, it has __________ days to commence closure.

(a) 10

(b) 20

(c) 30

(d) 40

I have been asked this question in a national level competition.

My enquiry is from Landfill Disposal in portion Landfill Disposal of Hazardous Waste Management

1 Answer

0 votes
by (424k points)
Right choice is (c) 30

The explanation is: After landfill unit receives last shipment of hazardous waste, it has 30 days to commence closure preparations and 180 days to complete all closure activities.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...