In a day, the top surface of rigid pavement ______ than the bottom of slab.

(a) expands

(b) contracts

(c) remains stable

(d) shows no changes

I got this question during an interview for a job.

Enquiry is from Design of Rigid Pavements in section Design of Flexible & Rigid Pavement of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
The correct choice is (a) expands

Easiest explanation: In a day, as the temperature in the top of rigid pavement is hot or at least more than that of the bottom, the the top surface of rigid pavement expands more than the bottom of slab.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...