The grip length of well is taken as _________ below the scour level in roads.

(a) ½ R

(b) 1½ R

(c) 1/3 R

(d) 1 R

This question was addressed to me in final exam.

The origin of the question is Analysis of Well Foundation topic in division Well Foundations of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
Correct answer is (c) 1/3 R

The best explanation: According to the code of practice of the Indian Road Congress, the grip length is taken as 1/3 R below the scour level.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...