Pneumatic caissons are closed at _________ during construction.

(a) Bottom

(b) Top

(c) Top and bottom

(d) None of the mentioned

This question was posed to me in a national level competition.

I would like to ask this question from Well Foundations topic in section Well Foundations of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
Correct choice is (b) Top

The explanation is: Pneumatic caissons are closed at the top and open at the bottom during construction.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...