The portion of backfill lying above a horizontal plane of wall is called ________

(a) surcharge

(b) base

(c) foot

(d) truss

This question was addressed to me in unit test.

The origin of the question is Earth Pressure Introduction topic in chapter Failure Envelopes & Earth Pressure of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
Correct option is (a) surcharge

The best I can explain: The portion of backfill lying above a horizontal plane of wall is called as the surcharge. The surcharge is a load which is imposed upon the surface of the soil close enough to the excavation to cause a lateral pressure to act on the system in addition to the basic earth pressure.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...