Total head is the sum of ________

(a) piezometric head and velocity head

(b) piezometric head and position head

(c) position head and velocity head

(d) velocity head and pressure head

I have been asked this question in final exam.

My question is from Seepage Analysis topic in division Seepage Analysis of Geotechnical Engineering I

1 Answer

+1 vote
by (727k points)
selected by
 
Best answer
Correct option is (b) piezometric head and position head

To explain: The total head is the sum of pressure head, velocity head and position head. The velocity head is considered negligible due to small flow of water. Therefore, total head is the sum of pressure head and position head.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...