The permeameter assembly is placed in ____________ of the Jodhpur permeameter apparatus.

(a) Bottom tank

(b) Top of cylinder

(c) Below the top plate

(d) None of the mentioned

This question was addressed to me in final exam.

The doubt is from The Jodhpur Permeameter topic in division Permeability of Geotechnical Engineering I

1 Answer

+1 vote
by (727k points)
selected by
 
Best answer
The correct answer is (a) Bottom tank

The best I can explain: The permeameter assembly is placed in the bottom tank having a water outlet which permits control of water level.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...