In which of the following units, design period is maximized?

(a) Distribution system

(b) Demand reservoir

(c) Water treatment unit

(d) Pipe mains

The question was posed to me in a job interview.

Question is from Water Demand topic in portion Water Demand and Quantity of Environmental Engineering

1 Answer

+1 vote
by (693k points)
selected by
 
Best answer
Correct choice is (b) Demand reservoir

The explanation is: Distribution system is designed for 30 years, the demand reservoir for 50 years, the water treatment unit for 15 years and the pipe mains for 30 years.

A B C D

1 2 3 4

2 3 4 1

2 1 4 3

1 2 4 3

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...