The general value of lift for concrete is taken as __________________

(a) 1.5 m

(b) 2.5 m

(c) 3 m

(d) 4 m

I had been asked this question by my college director while I was bunking the class.

This intriguing question comes from Gravity Dams in section Gravity Dam Design and Construction of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right answer is (a) 1.5 m

The best explanation: The concrete is poured from a certain height in the first attempt and this height is called a lift. Maximum height of single pour of concrete is usually about 1.5 m. If this is reduced, more horizontal joints will get developed.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...