The proportionality of APM was sacrificed to enable the outlet to carry higher silt charge by increasing the setting to 8/10.

(a) True

(b) False

This question was addressed to me during a job interview.

The origin of the question is Regulation Modules in chapter Regulation Modules and Canal Structure of Irrigation Engineering

1 Answer

0 votes
by (106k points)
Right answer is (a) True

Easiest explanation: The APM (Adjustable Proportional Module) has a setting of 6/10 which is aimed at exact proportionality. But the channels using such module silted very badly and hence, the setting was increased to 8/10 to enable the outlet to carry higher silt charge. The outlet is then known as A.O.S.M.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...