+1 vote
in Geotechnical Engineering II by (93.7k points)
The depth of the bore hole is checked at _________ before insertion of the under-reamer.

(a) At the start and At the end

(b) Each time

(c) None of the mentioned

(d) All of the mentioned

This question was posed to me in an interview.

The above asked question is from Construction of Under-Reamed Pile Foundation topic in division Pile Foundations of Geotechnical Engineering II

1 Answer

0 votes
by (243k points)
Right option is (a) At the start and At the end

Explanation: The depth of the bore hole is checked each time before insertion of the under-reamer so that any loose earth spilled from the bucket is removed.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...