A sequent peak algorithm is a plot between __________________

(a) Accumulated flow v/s time

(b) Discharge v/s time

(c) (Cumulative Inflow – Cumulative Outflow) v/s time

(d) Mass outflow v/s time

The question was posed to me at a job interview.

I'm obligated to ask this question of Reservoir Capacity Determination Using Hydrograph and Mass-curve in section Reservoirs and Dam Reservoirs Planning of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct choice is (d) Mass outflow v/s time

Explanation: It is a plot between time on X-axis and cumulative net flow on Y-axis. It is an excellent alternative to the mass-curve method of determining reservoir capacity. The positive value of cumulative net flow indicates a surplus of inflow and a negative value indicates a deficit of inflow.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...