What is the correct representation for the calculation of NIR?

(a) Cu – Re

(b) CIR + leaching losses

(c) FIR + conveyance losses

(d) FIR + leaching losses + conveyance losses

I had been asked this question during a job interview.

I need to ask this question from Water Requirements of Crops in portion Water Requirements of Crops of Irrigation Engineering

1 Answer

0 votes
by (106k points)
The correct option is (b) CIR + leaching losses

For explanation I would say: Net irrigation requirement (NIR) can be defined as the amount of irrigation water required to be delivered at the field to meet the evapotranspiration and leaching losses.

NIR = (Cu – Re) + amount of water required for leaching = CIR + leaching losses requirement.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...