Which of the following teams are involved in METOC?

(a) Crisis planning team

(b) Crisis management team

(c) Crisis Action team

(d) Crisis planning & Action team

This question was addressed to me in exam.

The question is from The Meteorological Anchor Desk System- Case Study I topic in portion Component Based Systems of Software Architecture

1 Answer

0 votes
by (46.2k points)
Right answer is (d) Crisis planning & Action team

The best I can explain: Crisis planning and action team are involved in METOC.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...