1cm per second settling velocity corresponds to a surface loading of ______ litre per day per m^2.

(a) 36000

(b) 864000

(c) 24000

(d) 6000

This question was addressed to me in an internship interview.

This interesting question is from Design Elements of Sedimentation topic in division Sedimentation of Environmental Engineering

1 Answer

+2 votes
by (693k points)
selected by
 
Best answer
The correct choice is (b) 864000

Easiest explanation: Surface loading = 864000*settling velocity = 864000*1=864000litre per day per m^2 where settling velocity is in cm/Sec.

Related questions

We welcome you to Carrieradda QnA with open heart. Our small community of enthusiastic learners are very helpful and supportive. Here on this platform you can ask questions and receive answers from other members of the community. We also monitor posted questions and answers periodically to maintain the quality and integrity of the platform. Hope you will join our beautiful community
...